When is payment due?
Whichever comes first: the date in your contract, or the Act’s date. Under the Act, payment is due:
- to a head contractor claiming from the principal: 15 business days after the claim was received (s 11(1A));
- to a subcontractor or supplier: 20 business days after the claim was received (s 11(1B)).
A contract term that sets a later date has no effect (s 11(8)).
Homes the owner lives in are different
For anyone working on a home the owner lives in or will live in — the builder and every subcontractor under them — the contract decides, or it’s 10 business days after the claim if the contract doesn’t say (s 11(1C)). There’s no limit: a 45-day contract term stands on a house.
Contracts can set an earlier date, and the standard home building contracts do — but they count days differently: the Building Commission NSW forms say 5 business days, HIA New Dwellings says 5 working days, and Master Builders BC4 says 5 banking days (or the period at Schedule 2 item 4(d)).
How long do they have to reply?
10 business days, or a shorter period in the contract, whichever ends first (s 14(4)). A contract can’t give them more time. If they don’t send a payment schedule in time, they owe the full amount and can’t raise any defence about the work if you go to court (s 15(4)).
How are business days counted?
Business days under the Act leave out weekends, NSW public holidays and 27–31 December (s 4). That last one is often missed — it’s why a claim sent in mid-December has a reply date well into January. A period set by your contract is counted the way the contract defines a day.
How long do I have to apply for adjudication?
It depends on what came back:
- A payment schedule for less than you claimed: 10 business days from the day you received it (s 17(3)(c)). This is the tightest deadline in the Act.
- A scheduled amount they didn’t pay: 20 business days from the due date (s 17(3)(d)).
- No payment schedule at all: first send a notice that you intend to apply, within 20 business days of the due date (s 17(2)(a)). They then get a second chance of 5 business days to send a schedule, and you have 10 business days to apply (s 17(3)(e)).
How the deadlines fit together
- One line makes it a payment claim. Saying it’s made under the Act (s 13(2)(c)) turns an invoice into a payment claim. Once received, every deadline starts — whatever the contract says about payment.
- They must reply in writing, fast. A payment schedule within 10 business days (or the contract’s shorter period), saying what they’ll pay and every reason for paying less. Any reason they leave out, they lose.
- If they say nothing, they owe it all. No schedule in time and no payment by the due date means they owe the full amount, with no counter-claim and no defence about the work — and your right to stop work applies.
- Each option has a time limit. The adjudication windows are 10 or 20 business days depending on what came back, and once they close, they’re gone. Suing for the debt has no such deadline.
The calculator’s timeline is these deadlines, worked out from your answers. “Between X and Y” means the date depends on a step you haven’t taken yet.