Don’t just hold the money until they fix it
It feels natural, and on a normal invoice it’s reasonable. Against a payment claim it’s the worst thing you can do. The law treats silence as agreement, and they can enforce the debt without proving the work was any good.
The defects are still real — you just lose the chance to raise them. Your payment schedule is where you make your case.
How long do I have to reply?
Whichever ends first (s 14(4)):
- 10 business days after you received the claim, or
- the period in your contract, if it’s shorter.
A contract can only give you less time, never more. The standard Building Commission NSW contract for work over $20,000 gives you 5 business days (clause 14). Contracts count days differently, so check how yours defines a “day”.
What happens if I don’t reply?
Once both your reply deadline and the payment due date have passed (s 15(1)):
- they can go to court to recover the unpaid amount as a debt — and you can’t counter-claim or raise any defence about the work;
- they can apply for adjudication, as long as you’ve been given a second chance to reply;
- they can stop work after 2 business days’ written notice that says it’s made under the Act.
When payment is due, explained →
What must my payment schedule say?
A payment schedule isn’t a letter saying you’re unhappy. The Act says exactly what it must contain (s 14(2), (3)):
- Which claim it replies to — their reference, the date and the amount claimed.
- How much you’ll pay — a number, even if it’s nil. “We’ll get back to you” isn’t an amount.
- Why it’s less than they claimed.
- Every reason you’re holding back payment — defects, unfinished work, back-charges, delay, materials not delivered, a variation you didn’t approve, an unlicensed contractor, a missing insurance certificate. All of it.
Leave a reason out and you can’t use it later
In adjudication you can’t raise any reason that wasn’t in your payment schedule (s 20(2B)) — not “we mentioned it on site”, not “they know”. And if you sent no schedule at all, you can’t respond in adjudication (s 20(2A)). Take time over it: your schedule is the limit of every argument you can make about this claim.
What your payment schedule must say, and which reasons work →
Does a missing supporting statement cancel the claim?
No. A head contractor claiming from a principal must attach a supporting statement (s 13(7)), and leaving it out is an offence — but the claim is still valid. Mention it in your payment schedule. Don’t ignore the claim because of it. What a supporting statement is →
How the deadlines fit together
- One line makes it a payment claim. Saying it’s made under the Act (s 13(2)(c)) turns an ordinary invoice into a payment claim. The deadlines run from the day you receive it, whatever your contract says.
- Reply in writing, in time. A payment schedule within 10 business days (or your contract’s shorter period), saying what you’ll pay and every reason for paying less.
- Silence counts as agreement. No reply and no payment by the due date means you owe the full amount, with no defence about the work.
- They have deadlines too. Their window to apply for adjudication closes; their right to sue for the debt doesn’t. If you get a notice that they intend to apply for adjudication, you have a final 5 business days to send the payment schedule you didn’t.
The calculator’s timeline is these deadlines, worked out from your answers. “Between X and Y” means the date depends on a step that hasn’t happened yet.